The project is in the finishing works stage.
In most apartments, GRC board has already been installed on the walls, and decorative finishing panels are in the process of being installed. So the apartments have started to take on their final appearance.

Ceramic Tile Installation Underway
Ceramic tile installation work continues. An Indonesian manufacturer was selected for the project

Ceiling Preparations in Progress
In units where electrical wiring and water supply pipes installation is complete, mineral wool sound insulation has been installed on the ceiling and a frame for the future drywall ceiling has been made. After all tests are conducted, the ceiling will be installed

Installation of Waterproof Membrane
The waterproof membrane installation has been completed on one of the buildings. Given the high rainfall intensity during Bali’s wet season, proper installation of quality material is critically important to prevent future leaks

Formwork Installation Completion
The formwork installation for the Joglo, which will serve as the entrance area and guest transit zone on the second floor, has been completed. The next step will be concrete pouring for the structure of this part of the project

Door Frame Ready for Installation
Door frames manufactured at a factory in Jakarta have been delivered to the project and are now ready for installation in the apartments. The next step will be the installation of doors

At the end of the month, according to the rules, a monthly meeting was held with representatives of the general contractor, quality manager, and other team members. The progress of work completed in December was reviewed, volumes were agreed upon, and plans for the next month were discussed.

At Marsa Construction Management, we never approve payment for completed works until we verify everything. If the reports contain works with incorrect volumes or that were not completed, they are not approved from our side, the amount is crossed out from the report and the developer does not pay for these works. Our clients only pay for the work and the volume that was completed by the contractor. Contact us today for more details.